Procedure 4-16: Install LNW80 switch pack

- Overview

Use this procedure to install LNW80 Switch circuit packs in Main slots M1 and M2.

The LNW80 Switch circuit pack has no optics and is used in headless main applications to allow full use of the VT1.5 switch fabric for VT1.5-type hairpin cross-connections. The LNW80 circuit pack supports equipment-related alarms.

The LNW80 Switch circuit pack requires no provisioning and does not support loopbacks, test access, performance monitoring, DCC functionality, incoming signal alarms, line timing, DS1 synchronization outputs, and upgrades. The LNW80 Switch circuit pack cannot be a cross-connection source or destination.

- Privilege level

You must log in as a Privileged, General, Maintenance, or Reports Only user to complete this procedure.

- Before you begin

Prior to performing this procedure:

  1. Refer to Required equipment and Before you begin in this chapter.

  2. Refer to Electrostatic discharge in Chapter 1, Safety.

  3. Obtain the work instructions for this procedure.

Steps

Perform the following to install LNW80 Switch circuit packs in Main slots M1 and M2.

 
1

Seat the first Switch Pack in Main slot M1.

Result:

The FAULT LED and ACTIVE LED lights. The FAULT LED flashes after about 20 seconds and then goes off. MJ or MN and NE alarm LEDs on the SYSCTL circuit pack light when the circuit pack is installed.


2

Seat the second Switch Pack circuit pack in Main slot M2.

Result:

The FAULT LED and ACTIVE LED lights. The FAULT LED flashes after about 20 seconds and then goes off. MJ or MN and NE alarm LEDs on the SYSCTL circuit pack light when the circuit pack is installed.


End of steps