SP-3 Site Preparation Grounding Checklist

Purpose

The following items must be completed prior to the installation of the cell site equipment. Circle the correct letter for the corresponding description items.

item #

 

Description

 

Yes

(Y)

 

No

(N)

 

N/A

 

Comments

 

1.

 

Is soil resistivity and site resistance test on file?

 

Y

 

N

 

N/A

 
 

2.

 

Have connection been provided to ground electrode system?

If yes, circle all that apply:

  1. Via a buried ring ground and driven rod(s)

  2. Via a buried metallic and electrically continuous water pipe

  3. Via driven ground rod(s) and/or plate(s)

  4. Via electrolytic ground rod(s)

  5. Via grounded building steel

  6. Via grounded grid or radial

 

Y

 

N

 

N/A

 
 

3.

 

Is lighting mast(s) or air terminal(s) provided and bonded?

 

Y

 

N

 

N/A

 
 

4.

 

Is antenna support structure(s) grounded?

 

Y

 

N

 

N/A

 
 

5.

 

Is antenna tower bonded to ground electrode system?

 

Y

 

N

 

N/A

 
 

6.

 

Are guy wires bonded to ground?

 

Y

 

N

 

N/A

 
 

7.

 

Are antenna cable shields grounded at both ends?

 

Y

 

N

 

N/A

 
 

8.

 

If tower is greater that 60 meters (200 ft.) high, are antenna cable shields grounded at mid-point and both ends?

 

Y

 

N

 

N/A

 
 

9.

 

Are all ground connections in compliance with Alcatel-Lucent requirements (exothermic weld, compression type with 2-hole lugs; properly secured; anti-oxidant used on contact surface area)?

 

Y

 

N

 

N/A

 
 

10.

 

Are all grounding conductors routed as straight as possible with no loops or sharp bends?

 

Y

 

N

 

N/A

 
 

11.

 

Are cabinet support structure grounded?

 

Y

 

N

 

N/A

 
 

12.

 

Are metallic conduits bonded at both ends and 7.62 meters (25 foot) intervals?

 

Y

 

N

 

N/A

 
 

13.

 

Are all fence corner posts and gate posts properly grounded (including fence fabric and barb wire, as applicable)?

 

Y

 

N

 

N/A

 
 

14.

 

Are all metallic objects within 1.8 meters (6 feet) bonded to the grounding system?

 

Y

 

N

 

N/A

 
 

15.

 

Is generator fuel tank bonded to the grounding system?

 

Y

 

N

 

N/A

 
 

16.

 

Is master ground bus in compliance with Alcatel-Lucent Equipment Drawings?

 

Y

 

N

 

N/A

 
 

17.

 

Is AC power supply equipped with a surge protection device and is the device properly connected to the ground system?

 

Y

 

N

 

N/A

 
 

18.

 

Is T1/E1 or T3/E3 line equipped with a surge protection device and is the device properly connected to the ground system?

 

Y

 

N

 

N/A

 
 

19.

 

Is tower light system (if installed) equipped with a surge protection device and is the device properly connected to the ground system?

 

Y

 

N

 

N/A

 
 