Workflow for independent NFM-P migration to a new NSP deployment
Description
The following is the sequence of high-level steps required to migrate from an NFM-P-only system to a new NSP cluster deployment that includes the NFM-P. Each cross-reference is a link to a section in procedure To migrate from an independent NFM-P system to an NSP cluster deployment.
Stages
1 |
Create the required NSP VMs in each data center, back up the NSP databases, and obtain the required security artifacts; see Prepare for migration. |
2 |
In each data center:
|
3 |
Configure each NFM-P main server to use the nspOS instance in the new NSP cluster; see Reconfigure NFM-P. |
4 |
Synchronize the NFM-P and NSP system data; see Synchronize system data. |
5 |
If the NSP deployment includes NSP analytics servers, configure each analytics server to use the nspOS instance and PostgreSQL database in the NSP cluster; see Reconfigure NSP analytics servers. |
6 |
If the NSP system includes the WS-NOC, configure the WS-NOC to use the nspOS instance in the NSP cluster; see Reconfigure WS-NOC. |