1 |
Open Network Intents.
|
2 |
In the upper right-hand corner of the Network Intents GUI, click More, Open Resource Management.
The Resource Management GUI opens in a separate browser tab.
|
3 |
Select a resource pool type from the drop-down list at the top of the GUI.
|
4 |
In the pools list, double-click the resource pool from which you want to reserve a resource.
The Pool Summary view opens.
|
5 |
Click Reserve Resource.
|
6 |
In the Reserve Resource form, specify the resource Reference and Owner in their respective fields.
|
7 |
Enable the Confirmed option to indicate that the resources are allocated and in use.
If the Confirmed option is not enabled, the resources are reserved with the implication that they will be in use.
|
8 |
Specify the resource values you are reserving in the Reserve Values field.
You can specify multiple resource values. After typing a value, click Add to add it to the list.
|
9 |
Enable the All Or Nothing option if you want the resource reservation to go ahead only if all of the specified resources are available to be reserved.
If the All Or Nothing option is disabled, the system reserves only the resources that are available.
|
10 |
Click Submit to reserve the resources.
End of steps |