Power up and power down | |||
GO |
This topic describes the steps to power up or power down a Lucent CM server or the Lucent CM system (all servers).
Procedure 1 |
Refer to |
Hardware installation |
Sun FireTM X2100 M2 Server Installation Guide |
Cabling | |
Power up | |
Power down |
1 | Some procedures are also available in other X2100 M2 guides. |
Procedure 1 |
Refer to |
Hardware installation |
Sun FireTM X2100 Server Getting Started Guide |
Cabling | |
Power up | |
Power down |
1 |
Procedure 1 |
Refer to |
Hardware installation |
Sun FireTM V20z and Sun FireTM V40z Servers Installation Guide |
Cabling | |
Power up | |
Power down |
Sun FireTM V20z and Sun FireTM V40z Servers User Guide |
1 |
The procedure is valid for all types of nodes (A-node, D-node and U-node).
Perform the following steps to power down a single Lucent CM server:
The procedure is valid for all types of nodes (A-node, D-node and U-node).
Perform the following steps to power up a single Lucent CM server:
Perform the following steps to power down all servers of Lucent CM system:
Perform the following steps to power up all servers of Lucent CM system: