How do I upgrade software on an NE?
Purpose
This procedure shows the process of upgrading software on an MDM-managed 7750 SR NE. Before performing this procedure, verify that the NE to be upgraded is reachable, and that adaptors for the new software version are installed on the NSP.
Nokia recommends using the nsp-ne-upgrade-with-phases operation type to upgrade a 7750 SR. When you create an operation with this operation type and NE type, the parameter values are provided as input for the upgrade workflow. NSP monitors the status of workflow executions.
Note: Scale limits apply for number of concurrent executions and number of targets per operation; see Scale limits for large-scale operations in the NSP Planning Guide.
The following table shows the general process for this example procedure.
Steps
1 |
Perform How do I import a node software image?. | ||||||||||
2 |
Open Device Management, All Operations. | ||||||||||
3 |
| ||||||||||
4 |
In the form that opens, click OPERATION TYPE. | ||||||||||
5 |
In the Select an Operation Type form, choose nsp-ne-upgrade-with-phases and click ADD. Fields required for the operation appear in the Operation Inputs pane. | ||||||||||
6 |
In the Basic Info panel, enter a name for the operation and an optional description. You can identify the operation by the name you enter. | ||||||||||
7 |
In the Select Targets panel, click SELECT, Resources, Network Elements. | ||||||||||
8 |
In the Select Network Elements form, choose one or more NEs to add them to the Bin on the right of the form. Use the fields above the list of NEs to filter the list as needed. | ||||||||||
9 |
Click ADD. The NEs you selected appear in the Select Targets panel. You can change the list of selected targets if needed:
| ||||||||||
10 |
In the Operation Inputs panel, configure the mandatory parameters:
| ||||||||||
11 |
Configure the Advanced Inputs as needed: | ||||||||||
12 |
In the Schedule panel, configure scheduling for each phase of the upgrade. For example, you can configure the operation to run the pre-check phase immediately and the software download phase as soon as the pre-checks are complete, and complete the activation and reboot during a maintenance window. For the pre-check phase: Set up the schedule. For each subsequent phase:
| ||||||||||
13 |
Click RUN. The operation appears in the All Operations view and begins executing according to the schedule. End of steps |