Important!
This is not a stand-alone procedure. Perform this procedure only as directed by another procedure.
Important!
When optical fibers are disconnected during this procedure, inc. LOS alarms are reported. The holdover mode active condition may also be reported depending on the provisioned system timing mode.
Complete the following steps to back out an OC-3 1+1 network to an OC-12 1+1 network upgrade where the nodes are connected using the Main slots at both nodes.
1 |
Identify the last node that was upgraded.
Reference: Procedure 14-2: Connect Personal Computer (PC) and establish WaveStar® CIT session | ||||||||
2 |
If required at the near-end node (starting node), verify the active/standby status of the OC-12 circuit pack in Main slot M2 and perform manual switches to switch traffic away from an active circuit pack. If the working card (slot 1 card) is to be upgraded and is active, perform an optional manual transmission switch. If the protect card (slot 2 card) is to be upgraded and is active, perform an optional manual transmission switch. Reference: Procedure 12-20.4: Verify active/standby status of circuit pack to be replaced | ||||||||
3 |
Identify and log in to the far-end node in the 1+1 network. Reference: Procedure 14-2: Connect Personal Computer (PC) and establish WaveStar® CIT session | ||||||||
4 |
If required at the far-end node, verify the active/standby status of the OC-12 circuit pack in Main slot M2 and perform manual switches to switch traffic away from an active circuit pack. If the working card (slot 1 card) is to be upgraded and is active, perform an optional manual transmission switch. If the protect card (slot 2 card) is to be upgraded and is active, perform an optional manual transmission switch. Reference: Procedure 12-20.4: Verify active/standby status of circuit pack to be replaced | ||||||||
5 |
Important! If the circuit pack is active for timing and/or transmission, opening the latch causes timing and/or transmission switches. Transmission hits (less than 60 ms) will occur for each separate protection switch. Do not reconnect the optical fibers until instructed to do so. The optical fibers are reconnected after the OC-12 circuit pack is backed out at each end of the optical span. At the near-end node, open the faceplate latch on the OC-12 OLIU circuit pack in Main slot M2. Disconnect the optical fibers from the OC-12 OLIU circuit pack in Main slot M2. Replace the OC-12 OLIU circuit pack in Main slot M2 with the original OC-3 OLIU circuit pack. Result: The original circuit pack in Main slot M2 is tested and autoprovisioned. The system reports an unexpected circuit pack type condition and an inc. OC12 LOS alarm for Main slot M2. Alarms may also be reported at other nodes. Reference: Procedure 4-2: Install OLIU circuit packs in Main slots | ||||||||
6 |
Important! If the circuit pack is active for timing and/or transmission, opening the latch causes timing and/or transmission switches. Transmission hits (less than 60 ms) will occur for each separate protection switch. At the far-end node, open the faceplate latch on the OC-12 OLIU circuit pack in Main slot M2. Disconnect the optical fibers from the OC-12 OLIU circuit pack in Main slot M2. Replace the OC-12 OLIU circuit pack in Main slot M2 with the original OC-3 OLIU circuit pack. Result: The original circuit pack in Main slot M2 is tested and autoprovisioned. The system reports an unexpected circuit pack type condition and an inc. OC12 LOS alarm for Main slot M2. Reference: Procedure 4-2: Install OLIU circuit packs in Main slots | ||||||||
7 |
At both ends of the optical span to be backed out, perform the following to connect the original OC-3 circuit pack in the Main slot M2 and the original OC-3 circuit pack in Main slot M2 at the opposite end of the original OC-3 optical span:
Result: The inc. OC12 LOS alarms clear. Transmission is now supported on the original OC-3 optical span. Reference: Procedure 14-4: Perform connection and verification of optical facility | ||||||||
8 |
If required at the far-end node, verify the active/standby status of the OC-12 circuit pack in Main slot M1 and perform manual switches to switch traffic away from an active circuit pack. If the working card (slot 1 card) is to be upgraded and is active, perform an optional manual transmission switch. If the protect card (slot 2 card) is to be upgraded and is active, perform an optional manual transmission switch. Reference: Procedure 12-20.4: Verify active/standby status of circuit pack to be replaced | ||||||||
9 |
If required at the near-end node, verify the active/standby status of the OC-12 circuit pack in Main slot M1 and perform manual switches to switch traffic away from an active circuit pack. If the working card (slot 1 card) is to be upgraded and is active, perform an optional manual transmission switch. If the protect card (slot 2 card) is to be upgraded and is active, perform an optional manual transmission switch. Reference: Procedure 12-20.4: Verify active/standby status of circuit pack to be replaced | ||||||||
10 |
Important! The UPD/INIT button does not work during this upgrade. At the far-end node, at the System View select Configuration → Update System → Upgrade. Select main-2 as the Directed Slot Choice and click OK. Result: A dialog box appears asking you to confirm executing this command. Click Yes. The unexpected circuit pack type condition for Main slot M2 clears, and the system reports an unexpected circuit pack type condition for Main slot M1. | ||||||||
11 |
Important! If the circuit pack is active for timing and/or transmission, opening the latch causes timing and/or transmission switches. Transmission hits (less than 60 ms) will occur for each separate protection switch. Do not reconnect the optical fibers until instructed to do so. The optical fibers are reconnected after the OC-12 circuit pack is backed out at each end of the optical span. At the far-end node, open the faceplate latch on the OC-12 OLIU circuit pack in Main slot M1. Disconnect the optical fibers from the OC-12 OLIU circuit pack in Main slot M1. Replace the OC-12 OLIU circuit pack in Main slot M1 with the original OC-3 OLIU circuit pack. Result: The original circuit pack in Main slot M1 is tested and autoprovisioned. The unexpected circuit pack type condition for Main slot M1 clears, and the system reports an inc. OC3 LOS alarm for Main slot M1. Alarms may also be reported at other nodes. Reference: Procedure 4-2: Install OLIU circuit packs in Main slots
| ||||||||
12 |
Important! The UPD/INIT button does not work during this upgrade. At the near-end node, select Configuration → Update System → Upgrade. Select main-2 as the Directed Slot Choice and click OK. Result: A dialog box appears asking you to confirm executing this command. Click Yes. The unexpected circuit pack type condition for Main slot M2 clears, and the system reports an unexpected circuit pack type condition for Main slot M1. | ||||||||
13 |
Important! If the circuit pack is active for timing and/or transmission, opening the latch causes timing and/or transmission switches. Transmission hits (less than 60 ms) will occur for each separate protection switch. At the near-end node, open the faceplate latch on the OC-12 OLIU circuit pack in Main slot M1. Disconnect the optical fibers from the OC-12 OLIU circuit pack in Main slot M1. Replace the OC-12 OLIU circuit pack in Main slot M1 with the original OC-3 OLIU circuit pack. Result: The original circuit pack in Main slot M1 is tested and autoprovisioned. The unexpected circuit pack type condition for Main slot M1 clears, and the system reports an inc. OC3 LOS alarm for Main slot M1. Reference: Procedure 4-2: Install OLIU circuit packs in Main slots
| ||||||||
14 |
At both ends of the optical span to be backed out, perform the following to connect the original OC-3 circuit pack in the Main slot M1 and the original OC-3 circuit pack in Main slot M1 at the opposite end of the original OC-3 optical span:
Result: The inc. OC3 LOS alarms clear. Transmission is now supported on the original OC-3 optical span Reference: Procedure 14-4: Perform connection and verification of optical facility STOP! To complete backing out the 1+1 network upgrade, return to the procedure that directed you to perform this procedure. End of steps |